[Hougang] Hougang Rivercourt


Thank you, Shao Ze, for providing this exciting status update!

1. BLK B completed. Water tank and roof been done. Removing tower crane now

2. Interior and electrical work for BLK B is completed. Doing minor rectification now

3. Aimed to start painting for BLK B at mid Sept

4. Car park completed (including basement)

5. All the above will be commencing for BLK A 1 month after BLK B which is mid Oct.

6. Shopping / Neighbourhood Centre – probably in 2 months.

Most importantly, they’re going to push earlier for TOP to EARLY APRIL!!

Advertisements
Categories: Progress TrackerTags: , , , , ,

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: